MDC2000 · AI INFERENCE AND TRAINING

Give 1,152 GPUs the infrastructure they need.

The MDC2000 modular GPU data center targets 2.5 MW of IT load for larger AI clusters. Power, direct liquid cooling and supporting air cooling are coordinated around the selected NVIDIA server configuration.

GB300 NVL72 CONFIGURATION
2.5 MW
Target IT load
142 kW
Maximum IT load per compute rack
1,152
GPUs in the GB300 NVL72 layout
1.10–1.15
Design PUE target

Design targets are checked against the selected hardware and complete load schedule. Energy and water performance depend on the site climate, operating load and cooling configuration.

High-density GPU data center infrastructure.

High-density GPU racks need electrical capacity, liquid interfaces, network space and service access that fit together. Supporting equipment still needs air cooling.

MDC2000 coordinates those systems in a prefabricated modular building, designed around the selected NVIDIA reference design and the site.

Four systems designed together.

  1. 01

    Power subassembly

    Low-voltage receiving interface, modular UPS, batteries and independent A/B/C/D rack distribution. Upstream MV switchgear, power transformers and standby generators are outside the base scope unless specifically included.

  2. 02

    IT environment

    32 racks in the GB300 layout: 16 compute racks and 16 network and service racks, with access to power, liquid connections and cabling.

  3. 03

    Thermal & facility subassembly

    Cooling-loop pumping, filtration, controls, leak monitoring and air-side cooling, with fire-protection and monitoring interfaces defined for the project.

  4. 04

    Heat rejection

    External heat rejection selected for the site climate and availability requirements. Dry operation can be supported by stored-water adiabatic assistance where needed.

Module geometry, transport splits and site connections are agreed during project engineering.

16 compute racks. 16 for networking and service.

The current GB300 NVL72 configuration provides 32 racks and hosts 1,152 GPUs in its 16 compute racks. Network and service equipment are selected around the cluster fabric.

Rack allocationQuantityDesign role
GB300 NVL72 compute racks161,152 GPUs in the GB300 NVL72 configuration
Network and service racks16Networking, storage and service equipment for the selected cluster
Total racks32Compute and support space in one coordinated facility

The current target is 2.5 MW IT load, with 142 kW per compute rack. The rack maximum is a design limit, not an instruction to multiply every rack by 142 kW. The final equipment schedule sets the total.

Select the complete NVIDIA configuration.

GB300

GB300 NVL72

16 compute racks plus 16 network and service racks, hosting 1,152 GPUs.

B300 / B200

Other NVIDIA server configurations

Discuss the selected B300 or B200 server arrangement. Rack power, cooling, networking and service geometry are checked for that equipment.

Platform positioning covers GB300, B300 and B200 configurations. The 1,152-GPU count belongs to the GB300 NVL72 layout; other server arrangements need their own rack and load plan.

Direct liquid cooling for compute, with supporting air cooling.

The current product direction uses an approximately 85% direct liquid / 15% air cooling split. Coolant carries heat from the main compute equipment; an air-side system serves the remaining components and supporting infrastructure.

85%Direct liquid cooling in the current design direction
15%Air cooling for residual and supporting loads

The coolant, CDU interfaces, flow rates and operating temperatures follow the selected OEM equipment and project design.

The split describes the design direction. The final thermal schedule establishes the actual liquid and air duties.

Low water use starts with the heat-rejection design.

Dry heat rejection is the starting strategy. Stored, treated water can support adiabatic assistance when the climate requires it.

MDC2000 targets PUE 1.10–1.15. The PUE range means facility energy is 10–15% above IT energy, making the infrastructure overhead clear. It depends on climate and load; it is a design target, not a measured result for every installation.

Annual modelling establishes the energy and water use for the site. Storage volume and refill arrangements are designed separately from annual consumption.

Designed around NVIDIA reference requirements.

The electrical design coordinates rack supply paths, UPS protection and supporting loads with the selected NVIDIA reference design.

Upstream sources, maintenance, fault domains and control sequences are reviewed as one availability design.

Uptime Institute requirements and OCP recommendations are assessed where relevant to the project. A reference-design statement does not claim a completed facility certification.

Design the GPU facility and site connections together.

  1. 01

    Confirm the equipment and location.

    Define the server configuration, network, storage, IT load, site climate and deployment plan.

  2. 02

    Approve the basis of design.

    Freeze electrical, thermal, civil, controls, fire and OEM boundaries.

  3. 03

    Complete detailed engineering.

    Review fibre routes, rack access, power paths, liquid interfaces, transport and outdoor heat rejection.

  4. 04

    Factory-integrate the AI Block.

    Assemble power, thermal, controls and monitoring systems in a controlled environment.

  5. 05

    Complete factory acceptance testing (FAT).

    Test the agreed electrical, thermal, control and alarm functions before shipment.

  6. 06

    Install and connect.

    Complete site works in parallel, then position and integrate the system.

  7. 07

    Complete SAT / IST and commissioning.

    Verify the transported and site-connected facility before operational handover.

The delivery programme separates factory work, transport, site installation and commissioning, with the dependencies for each stage agreed in the proposal.

Current product targets and project scope

Target IT load
2.5 MW
Maximum IT load per compute rack
142 kW
GB300 rack layout
16 compute + 16 network and service racks
GB300 GPU population
1,152 GPUs
Purpose
AI inference and training
Target equipment
NVIDIA GB300, B300 and B200 configurations
Cooling direction
Approximately 85% direct liquid / 15% air
Design PUE target
1.10–1.15; site climate and load dependent
OEM interfaces
Coolant, CDU, power and network interfaces agreed for the selected equipment
Heat rejection
Selected for the climate and availability requirements
Power architecture
Coordinated with the selected NVIDIA reference design
Project scope
Infrastructure, OEM equipment and site works defined separately
Acceptance
FAT before shipment; site acceptance, integrated testing where agreed, commissioning and handover

The final load and cooling schedule reconciles rack limits, total IT load, OEM interfaces and site climate. Numerical PUE values are design targets, with annual performance modelled for the project.

Agree the infrastructure and equipment scope.

INSIDE THE COORDINATED MDC2000 DESIGN

  • IT environment and rack service access
  • LV receiving interface, UPS, batteries and rack distribution
  • Facility cooling-loop distribution and air-side support cooling
  • Controls, monitoring and leak detection
  • Coordinated fire-protection, security and BMS/DCIM interfaces
  • Factory integration and the agreed FAT scope

CONFIRMED BY PROJECT

  • Compute, network and storage hardware
  • OEM rack and CDU secondary-loop implementation
  • Upstream MV switchgear and transformers
  • Standby generation
  • External heat-rejection equipment and redundancy
  • Site civil works, foundations, utilities and access
  • Fire detection/suppression equipment and local approvals
  • SAT, integrated testing, certification and operational support

FOR SITE OWNERS AND ENERGY COMPANIES

Build capacity for a tenant’s computing equipment.

MDC2000 can form the infrastructure for a colocation business. Alongside the facility, we can discuss introductions to prospective tenants and the requirements they bring. Tenant placement and commercial terms are agreed by project.

Tenant introductions do not guarantee occupancy or investment returns. MDC4000 is a coming-soon option for future capacity planning.

Frequently asked questions

How many GB300 NVL72 racks and GPUs does MDC2000 accommodate?

The current MDC2000 GB300 NVL72 layout has 16 compute racks and 16 network and service racks, hosting 1,152 GPUs. It targets 2.5 MW of IT load, with a 142 kW design basis per compute rack. The final equipment and load schedules establish the configuration-specific limits.

How does MDC2000 cool GB300 NVL72 equipment?

MDC2000 uses direct liquid cooling for the main GPU heat load and air cooling for residual heat and supporting equipment. Rack CDUs interface with the facility cooling loop, which carries heat to external dry coolers with adiabatic assistance where needed. OEM server interfaces and the site climate determine the final thermal design.

How much site power is needed for a 2.5 MW IT deployment?

The 2.5 MW figure is MDC2000's target IT load, not the required grid connection. Incoming power must also cover cooling, electrical losses and other facility loads, including the relevant peak and operating conditions. A site load study sizes that supply; an annual PUE target alone cannot do so.

Does MDC2000 need a permanent water connection?

The MDC2000 reference uses dry heat rejection first, with tank-fed adiabatic assistance in hot conditions. That strategy can operate without a permanent utility-water connection, but it still needs treated-water storage and a refill plan where adiabatic operation is required. Annual use and tank sizing follow the site climate and operating profile.

What PUE should I use when planning an MDC2000 project?

The current published MDC2000 design target is PUE 1.10–1.15. It is not a measured operating result for every installation. A project energy model must state the climate, IT-load profile, cooling modes and energy boundaries before the target can be used in operating-cost assumptions.

Is MDC2000 a single 40-foot container?

MDC2000 is a prefabricated modular building assembled from transportable technical sections. Its layout includes compute and support racks, service circulation and technical systems. Final dimensions, foundation loads, access openings and external cooling clearances come from the configuration-specific project drawings.

What is included in the MDC2000 infrastructure scope?

The scope defines IT space, facility power distribution, cooling, controls and the associated interfaces. Servers and GPUs are separately identified. Upstream medium-voltage switchgear, power transformers and standby generators are outside the issued base scope unless specifically included. The proposal also assigns site works, installation and commissioning responsibilities.

Can MDC2000 support a GPU colocation business?

MDC2000 can provide infrastructure for a site owner hosting a tenant's computing equipment. Facility ownership, GPU ownership, operations and maintenance need separate responsibilities and commercial terms. ModulEdge can discuss prospective tenant introductions alongside the infrastructure project; an introduction does not establish a tenant commitment or investment return.

What evidence should I request for compatibility and resilience?

Request the approved OEM equipment list, rack power and cooling interfaces, project topology and acceptance-test scope. Any claimed certificate should identify its issuer and the design, product or facility it covers. Reference-design alignment, factory testing and a completed site certification are different forms of evidence.

Plan the facility for your AI cluster.

Share the hardware plan, available power or location. We will discuss the infrastructure and, for colocation projects, the potential tenant requirements.

Contact form

Preview build: this form is not connected yet, so nothing was sent.