ENTERPRISE AI
Infrastructure for your own AI workloads
Coordinate the facility with the systems your team will operate. Define the rack configuration, network and storage, workload requirements and operating plan before freezing the design.
MDC3000 · AMD HELIOS INFRASTRUCTURE
MDC3000 brings 2.75 MW of target IT capacity into a prefabricated modular building. Power, liquid cooling and service space are coordinated for ten AMD Helios compute racks and 16 racks for networking, CPU and storage.
Current design figures. Final power, cooling and rack schedules are coordinated with the selected OEM equipment and site conditions. IT load and total incoming power are separate design quantities.
Rack-scale AI needs more than space for compute racks. Power distribution, liquid connections, network and storage equipment, residual air cooling and maintenance access have to work together.
MDC3000 coordinates these systems around AMD Helios in one prefabricated modular facility, for enterprise AI, inference services and training workloads.
Incoming power, UPS, batteries and rack distribution coordinated for the Helios equipment schedule. The current design calls for 3.2 MW of total incoming power; upstream equipment and supply boundaries are agreed in the project scope.
Ten wide-format AMD Helios compute racks and 16 network, CPU and storage racks. The IT-hall access openings are adapted for the wider compute equipment and its installation and service requirements.
Liquid-cooling distribution, pumping, controls, leak monitoring and supporting air cooling, with fire-protection and monitoring interfaces coordinated for the project.
Outdoor heat rejection selected for the climate and availability requirements. The design starts with dry heat rejection and provides for adiabatic assistance where conditions require it.
The building retains the external dimensions and appearance of the existing modular platform. The Helios rack layout, access openings, transport splits and service clearances are detailed for the selected equipment.
The Helios configuration separates wide compute racks from the supporting equipment. All 26 rack positions are included in the coordinated facility layout.
| Rack allocation | Quantity | Design role |
|---|---|---|
| AMD Helios compute racks | 10 | Wide-format rack-scale compute equipment |
| Network, CPU and storage racks | 16 | Cluster networking, CPU services and storage |
| Total racks | 26 | Compute and supporting IT equipment |
The 2.75 MW IT-load target covers the complete IT configuration. It is not a per-rack rating: the final rack schedule allocates power between compute and supporting equipment.
ENTERPRISE AI
Coordinate the facility with the systems your team will operate. Define the rack configuration, network and storage, workload requirements and operating plan before freezing the design.
AI SERVICE OPERATORS
Plan compute, supporting IT, cooling and available site power together. Align equipment procurement, facility delivery and commissioning with the capacity you intend to bring into service.
The selected OEM system sets the rack dimensions, weight, power connections, cooling interfaces and service requirements. Equipment availability and the delivery programme are agreed for the project.
The current design direction is approximately 85% direct liquid cooling and 15% air cooling. Liquid cooling serves the main compute load; air cooling removes residual heat and heat from supporting equipment.
Coolant specification, CDU arrangement, flow rates and operating temperatures are coordinated with the selected Helios OEM system.
The 85% / 15% split is an approximate design allocation. The project thermal schedule establishes the actual liquid and air duties.
The facility cooling loop recirculates coolant. Dry heat rejection is the starting strategy, with adiabatic assistance where the climate requires it.
Annual energy and water use depend on the location, IT-load profile, equipment and cooling controls. The project model establishes the expected PUE, water demand and any storage or refill requirements.
The current MDC3000 design separates power for compute and supporting IT from the total incoming supply, which also serves cooling, electrical losses and facility systems.
The final electrical study confirms the connection, UPS arrangement, rack feeds, maintenance modes and redundancy for the selected hardware and site.
Annual energy performance is modelled for the site climate, operating load and cooling configuration.
Define the Helios OEM configuration, network, storage, IT load, site climate and deployment plan.
Freeze electrical, thermal, civil, controls, fire and OEM boundaries.
Review wide-rack access openings, installation routes, fibre routes, rack power, liquid interfaces, transport and outdoor heat rejection.
Assemble power, thermal, controls and monitoring systems in a controlled environment.
Test the agreed electrical, thermal, control and alarm functions before shipment.
Complete site works in parallel, then position and integrate the system.
Verify the transported and site-connected facility before operational handover.
The delivery programme separates factory work, transport, site installation and commissioning, with the dependencies for each stage agreed in the proposal.
These figures describe the current MDC3000 design. The project basis of design confirms the equipment, operating conditions, power and thermal schedules, redundancy and scope of supply.
FOR SITE OWNERS AND ENERGY COMPANIES
MDC3000 can provide the facility for a tenant operating AMD Helios equipment. Coordinate the power, cooling and service space with the tenant’s cluster requirements, and discuss potential tenant introductions where relevant.
Tenant introductions and commercial terms are project-specific; occupancy and investment returns are not guaranteed.
MDC3000 is ModulEdge's prefabricated modular data-center design for ten AMD Helios compute racks and 16 network, CPU and storage racks. Its current published target is 2.75 MW of total IT load for enterprise AI, inference and training. The approved OEM equipment schedule defines the rack configuration.
The 2.75 MW target covers the selected computing and supporting IT equipment. The current 3.2 MW incoming-power design figure also accounts for facility loads. They are different electrical boundaries. The project load study confirms the required supply and operating assumptions rather than deriving them from rack count alone.
The current MDC3000 design direction is approximately 85% direct liquid cooling and 15% air cooling. The selected Helios equipment establishes the liquid and residual-air duties, coolant requirements, CDU arrangement and operating temperatures. Those interfaces require an AMD/OEM-specific schedule rather than values copied from a GB300 configuration.
The layout review covers rack dimensions and weight, IT-hall access openings, maintenance access, power delivery and cooling connections. The site also needs the defined foundations, external heat-rejection space, lifting route and fibre connections. Wider rack-scale equipment must be checked against the actual delivery and service route.
MDC3000 energy and water performance are modelled for the site climate, IT-load profile and selected cooling plant. Dry heat rejection is the starting approach, with adiabatic assistance where required. A closed facility loop does not establish zero water consumption or a universal PUE.
The core offer is the infrastructure around the computing systems. The proposal states who supplies the Helios racks, networking, CPU and storage equipment and where the OEM cooling interfaces sit. Their procurement, installation and acceptance responsibilities must be included explicitly when comparing project prices.
Start with the OEM equipment list, target IT load, project location, available power and required date. Engineering then resolves the rack, electrical, cooling and site interfaces. The quotation sets the supply boundary, resilience and acceptance criteria; the programme identifies hardware availability, factory testing and site-readiness dependencies.
Share your hardware plan, site location and available power. We will discuss the rack layout, infrastructure scope and delivery programme.