Behind-the-Meter Data Center Siting: An AI Cluster Playbook for Energy Companies
A behind-the-meter data center skips grid queues (2,600 GW, 5-yr wait): siting and sizing 10-20MW modules for energy companies.
By Yuri MilyutinManaging Partner, ModulEdge

A behind-the-meter data center draws from on-site generation rather than relying solely on a new grid-import connection. It can reduce some connection dependencies, but co-location still needs the applicable network studies, agreements and approvals. For a first energy-site development, a 10–20 MW phased block may be one screening case; its feasible size follows firm usable power, the tenant and the site. That block can contain multiple modular facility units.
This post picks up where the stranded-power business case ends and walks through how to screen a candidate site, size the first module, get through interconnection and permitting, pick a contract structure, and match infrastructure to a site that was never meant to host a data center.
What Is a Behind-the-Meter AI Cluster, and Why Does It Start at 10-20 MW?
Most energy executives hear “AI data center” and picture Stargate or Meta’s Hyperion campus in Louisiana, which is scaling toward 5 GW through 2030 on a reported $50 billion budget. That reference point kills good projects before they start. A behind-the-meter cluster at a wind farm, biogas site, or gas peaker solves a much narrower problem than those campuses ever will: what to do with power that’s already stranded, curtailed, or underused at a site that will never see gigawatt-scale transmission investment.
Behind-the-meter (BTM) means the compute load sits on the generation side of the meter, drawing electricity that hasn’t yet been sold onto the grid. Cleanview’s 2025 tracking identified 46 U.S. data center projects planning roughly 56 GW of behind-the-meter capacity, with about 90% of that pipeline (close to 50 GW) announced in 2025 alone. Most of it is gas. Texas leads, on the strength of Permian Basin supply, pipeline density, and a permitting environment built for speed.
That 56 GW figure spans peaker-scale projects and campuses. A candidate site needs usable generation, an agreed connection arrangement and a compute load whose operating profile it can support. A short private wire can simplify the physical connection, but does not by itself remove utility studies, network upgrades or regulatory review.
This playbook focuses on inference-oriented projects; training can also be hosted when the power, cooling and network topology fit. Here a 10–20 MW “module” means a phased site block assembled from facility units, rather than one factory-delivered container. Dividing 10 MW by a 120–140 kW compute-rack allowance gives roughly 70–80 racks before network, support and facility loads; 20 MW gives roughly 140–160. These are arithmetic screens, not a completed cluster design.
What Makes a Generation Site a Good Candidate for Compute?
Not every substation or well pad qualifies. Some sites have curtailment on paper but no realistic way to get a compute load connected without a multi-year transmission project, which defeats the entire point of going behind the meter.
The strongest candidates have real surplus or curtailed capacity and a short physical run to an interconnection point. Spare land helps. So does switchgear that already handles the voltage class a 10-20 MW load needs. Miss two of these and the project usually isn’t worth pursuing at this size.
We’ve made the economic argument for monetizing stranded power elsewhere — the curtailment losses, the flared-gas volumes, the margin gap between selling power at grid rates and hosting compute (see Turning Stranded Power Into Cash Flow). This post assumes you’re already convinced and goes straight to the site walk. The general fundamentals of evaluating any data center site, power and land and connectivity, still apply here, just weighted differently for a generation-adjacent site than for a traditional colocation build.
| Criterion | What “good” looks like | Why it matters |
|---|---|---|
| Surplus / curtailed capacity | 15-25 MW consistently available above existing offtake | Leaves margin above a 10-20 MW draw for ramp-up and redundancy |
| Distance to interconnection point | On-site, or within reach of existing switchgear | Avoids new transmission lines and multi-million-dollar contribution charges |
| Existing switchgear / voltage class | 13.8-34.5 kV feeders already present | Determines whether a new substation is needed at all |
| Land | 1-3 acres for a 10-20 MW modular footprint | Modular capacity needs pad space, not a campus master plan |
| Generation firmness | Gas, biogas, or nuclear preferred; wind/solar workable with storage or curtailable load | Determines whether compute runs continuously or must flex with output |
| Regulatory posture | State or ISO has defined co-location rules | Sets the permitting timeline and any curtailment obligations |
Generation firmness deserves a second look. Gas peakers and biogas digesters produce something close to dispatchable, predictable power, which is easy for a compute tenant to underwrite. Wind and solar sites can absolutely work. Texas regulators approved a 260 MW AI data center co-located with a similarly sized wind farm in July 2026, but the compute load has to tolerate variability, or the site needs storage to smooth it.
Why Is 10-20 MW the Right First Module, Not a Gigawatt Campus?
Gigawatt campuses are impressive, and mostly irrelevant to a mid-size utility or an independent power producer sitting on one gas peaker. Meta’s Hyperion is scaling to 5 GW. OpenAI’s Stargate venture with Oracle and SoftBank has roughly 7 GW planned. Neither is a utility-scale AI data center in the sense this playbook cares about: both require dedicated transmission-class substations at 138-230 kV, multi-year permitting cycles, and capital measured in tens of billions.
None of that is available, or necessary, at a 40 MW gas peaker or a 120 MW wind farm carrying 20 MW of chronic curtailment.
A 10-20 MW module fits behind the switchgear most mid-size generation sites already own; many can interconnect at an existing 34.5 kV feeder without a new substation. It’s small enough that a single generation asset, even a modest one, can supply it without threatening the site’s primary job, whether that’s selling power under an existing PPA or running an oilfield. And at this size an operator can prove the model (construction time, interconnection process, contract terms, uptime) before staging up.
Staging matters because most sites don’t have 100 MW of stranded capacity sitting idle on day one. They have 10 MW, with another 10-15 MW likely once curtailment patterns firm up or a second turbine comes online.
| Phase | Compute capacity | Approx. GB200-class racks | Footprint | Typical interconnection |
|---|---|---|---|---|
| Phase 1 | 10 MW | ~70-80 racks | 1-1.5 acres | Existing feeder, 13.8-34.5 kV |
| Phase 2 | +10 MW (20 MW total) | ~140-160 racks | 2-3 acres | Same feeder, or an added switchgear bay |
| Phase 3 (optional) | +20-40 MW (40-60 MW total) | ~280-400+ racks | 4-6 acres | Dedicated substation likely required |
Past Phase 3, the project starts to resemble the gigawatt campuses this playbook is explicitly not written for. Different capital stack. Different timeline. Different buyer.
How Does Behind-the-Meter Interconnection and Permitting Actually Work?
The entire appeal of BTM siting is skipping the queue. That’s not automatic, and the rules are moving fast enough that “how it worked last year” isn’t a safe assumption to build a deal on.
At the federal level, FERC directed PJM, the largest U.S. grid operator, in a December 2025 order to create new rules specifically for co-located data center load, formalizing a category that had previously been argued case by case. Regulators, in other words, are catching up to a model that’s already being built on the ground. Nobody should read that as permission to skip review.
State rules vary more, and Texas shows where this is heading. Senate Bill 6, signed in June 2025, gave ERCOT authority to disconnect co-located large loads during grid emergencies and required Public Utility Commission of Texas review for any new load of 75 MW or more seeking to co-locate with an existing generator. Loads above that threshold must be able to curtail their full draw within 30 minutes during an emergency. A 10-20 MW first module sits comfortably under that line in ERCOT. That’s one more reason starting small is often the lighter regulatory lift.
Below the review thresholds, expect a standard permitting checklist regardless of jurisdiction: air permits if pairing with new gas generation, water discharge permits if cooling requires anything beyond a closed loop or air, local zoning or conditional-use approval for the structure itself, and utility notification even when no new grid interconnection is being requested. None of it is unique to compute — it’s the same environmental and safety review any new load addition at a generation site would trigger.
The ground keeps shifting under bigger deals, which is instructive even at 10-20 MW scale. Talen Energy’s original arrangement to sell Amazon up to 1,920 MW behind the meter from its Susquehanna nuclear plant was restructured in June 2025 into a grid-connected, front-of-the-meter retail deal, after a FERC ruling created uncertainty around the original co-location structure. Build the first module to survive a reclassification. Don’t assume today’s BTM rules are permanent.
What Contract and Ownership Structures Can Energy Companies Offer?
Three structures cover most real deals, and the right one depends on how much operational risk the energy company wants to carry.
Colocation lease. The energy company acts as landlord, supplying the agreed site and facility services to a tenant that owns and operates its IT. Revenue can combine contracted capacity rent and a metered power pass-through; the lease defines the exact scope. Compare this revenue with the landlord’s facility, financing and operating costs. Gross compute-service revenue earned by a GPU operator is a different business and should not be used as the landlord’s rental yield. The cost components are developed in modular data center cost.
Tolling agreement. Common in battery storage, and increasingly relevant to gas-paired compute: the compute operator, the “toller,” pays a fee for the right to run its own dispatch decisions through a plant the energy company still owns and physically operates. The energy company keeps O&M control and the underlying asset. The toller gets flexibility over when and how much power it draws. This hands over less operational control than a lease, which matters if the generation asset also serves other customers or existing grid obligations.
Joint venture. The energy company contributes site, power rights, and interconnection standing; a compute operator or infrastructure investor contributes capital and demand. Google’s December 2024 agreement with Intersect Power is worth studying here: co-locating data centers inside roughly $20 billion of renewable energy parks, with the first phase targeted for 2026. JVs carry the most complexity and the most upside. They’re also the structure most exposed to the kind of regulatory reclassification that hit Talen’s original Amazon arrangement.
Whichever structure you choose, treat contract term and regulatory assumption as separate risks. A 15-20 year colocation lease signed under today’s BTM rules needs explicit language for what happens if a state or ISO reclassifies co-located load mid-contract. Texas, PJM, and FERC all changed their rules in 2025 alone.
Why Does Factory-Built Modular Fit Distributed Generation Sites Better Than Custom Construction?
A custom-built data center wants a flat site with permanent access roads, plus a demand forecast that holds for the 18-36 months a traditional build typically takes. A wind farm’s substation yard, a biogas digester’s fence line, or an oilfield pad rarely offers any of that. The site was chosen for wind speed or gas geology, not construction logistics. It usually sits well outside anywhere a general contractor wants to mobilize a crew for three years.
Factory manufacture can overlap with parts of the site programme, but delivery still needs an approved facility and campus design. A 10–20 MW cluster requires a plan for shared power, cooling, connectivity and operating states. For ModulEdge, environmental limits and protection are specified for the selected equipment and location; there is no single temperature rating for the entire range. See our mobile and portable modular siting playbook for the site and transport interfaces.
Staged, modular capacity matches how stranded power actually shows up in the field. MARA doubled its flared-gas hosting capacity to 50 MW across Texas and North Dakota sites in partnership with NGON in late 2025, and it did so by adding standardized modular capacity at multiple wellhead locations as gas volumes justified it rather than building one large facility. Vespene Energy took the same approach to landfill gas, pairing on-site generation equipment with data processing load at a municipal landfill in Marathon County, Wisconsin. Neither looks anything like a hyperscale campus, and both look exactly like the kind of site this playbook is written for. Renewable-paired sites raise a related set of questions we cover separately in the solar-powered data center.
A fixed building bets the entire capex on one forecast. Modular capacity lets an energy company add the next 10 MW when the second turbine or the next well comes online. It lets them stop cleanly if it doesn’t.
How Should an Energy Company Decide Where to Start?
Screen for a site with real surplus, a short wire to existing switchgear, and a generation type your compute partner can live with. Firm gas and nuclear are the easiest sell. Wind and solar take more structuring, but they work.
Use 10–20 MW as one first-phase screening case, then size the phase to firm usable power, the tenant and site constraints. Pick a contract structure that matches how much operational control you’re willing to give up: lease for simplicity, tolling for shared risk, joint venture for the sites worth building a real partnership around. Then build in modular capacity rather than a permanent structure, because the next phase, and the regulatory rules governing it, may not look like this one. The full delivery model, from spec to commissioning, is in our definitive guide to modular data centers.
The energy companies moving now are trading a stranded asset for a contracted one. The ones still waiting are still deciding whether their surplus power is a liability at all.
Behind-the-meter power is one input to a tenant-ready site. ModulEdge needs the generation and load profiles, grid operating limits, fuel assumptions, connectivity and intended rack configuration to define the facility interfaces. Commercial power terms, permissions and the compute tenant remain separate parts of the project.
Frequently Asked Questions
What is a behind-the-meter data center? A behind-the-meter data center draws power directly from a generation asset (a gas plant, wind farm, solar array, biogas site, or nuclear facility) before that electricity crosses the utility meter and enters the public grid. Because the load never touches the transmission network in the same way a new grid-connected project does, it can often avoid the multi-year interconnection queue, which the Lawrence Berkeley National Lab measured at roughly 2,600 GW of pending capacity and a five-year median wait as of 2024.
Why is 10-20 MW considered the right first size for an energy company’s AI cluster? A 10–20 MW phased site block can be a useful screening case for a generation owner. Existing feeders and switchgear must be checked for usable capacity, fault duty, protection and permitted operation; that size does not automatically avoid a substation upgrade. The article’s rack counts are preliminary arithmetic before network and facility loads, not a completed cluster design. The tenant and site determine the first viable phase.
How much surplus or curtailed power does a site need to host a 10 MW compute cluster? Most operators target 15-25 MW of consistently available surplus or curtailed capacity to host a 10 MW draw, leaving margin for ramp-up, redundancy, and a future expansion to 20 MW. The exact number depends on how firm the generation source is: gas and nuclear sites typically need less margin than wind or solar sites with variable output.
Do I need FERC or state utility approval to co-locate compute behind my meter? It depends on load size and jurisdiction. FERC’s December 2025 order directs PJM to create new rules specifically for co-located data center load, while Texas already has a statute: Senate Bill 6 (June 2025) requires Public Utility Commission of Texas review for any new load of 75 MW or more co-locating with an existing generator, plus a 30-minute emergency curtailment capability. A 10-20 MW first module generally sits below that review threshold.
What’s the difference between a colocation lease and a tolling agreement for energy-to-compute deals? A colocation lease makes the energy company a landlord: it charges a compute operator base rent for capacity plus a metered power pass-through, and the operator owns and runs its own IT equipment. A tolling agreement keeps the power plant under the energy company’s ownership and operation, with the compute operator paying a fee for the right to draw power on its own schedule, which hands over less operational control than a lease.
Can curtailed solar or wind power a behind-the-meter AI cluster, or does it need to be gas or nuclear? Renewables can work, but variability changes the deal terms. Texas regulators approved a 260 MW AI data center co-located with a similarly sized wind farm in July 2026 under a net metering arrangement, though the load must be able to curtail fully within 30 minutes during grid emergencies. Firm generation types (gas peakers, biogas, nuclear) require less compute-side flexibility and are generally the simpler first pairing.
Why not skip straight to gigawatt scale if hyperscalers are already building at that size? Gigawatt campuses like Meta’s Hyperion, scaling toward 5 GW through 2030, or OpenAI’s Stargate, with roughly 7 GW planned, require dedicated transmission-class substations, multi-year permitting, and tens of billions in capital that most utilities, IPPs, and independent generation owners neither have nor need for a first deployment. A 10-20 MW module proves the operational model on a single generation asset before any larger commitment is considered.
How fast can a 10-20 MW modular data center actually be deployed at a generation site? The operating date follows the agreed factory, transport, site-integration and acceptance programme. A 10–20 MW phase may use multiple units and shared power, cooling and network systems. Existing generation does not by itself establish readiness; utility studies, permits, equipment availability and commissioning can control the date.


