AI infrastructureUpdated 18 min read

AMD Helios: Rack Design, Power and Cooling Requirements

Translate Helios rack-scale architecture into a facility brief, with current AMD status, a reference-design power example and the OEM data required for engineering.

Yuri MilyutinBy Yuri MilyutinManaging Partner, ModulEdge

Conceptual illustration of a wide AI server rack with power and liquid-cooling interfaces, with the headline "Start with the rack. Then design the facility."

Updated 4 November 2026: Added an AMD Helios vs NVIDIA GB300 NVL72 comparison, ModulEdge’s pricing and lead-time view, software guidance and the MDC3000 facility design.

AMD Helios is a rack-scale reference design whose deployed configuration comes from an OEM or ODM. For facility planning, AMD and Schneider Electric’s August 2026 reference design supports racks up to 246 kW. Treat that as a reference-design envelope: the power, cooling, dimensions and service requirements for a purchased Helios system must come from its specific supplier.

Helios puts the rack configuration ahead of the building layout. A room designed around familiar rack widths or an older GPU load allowance can miss the power connections, liquid interfaces and access space required by the selected system. Resolve these requirements before freezing a modular facility, electrical package or outdoor cooling plant.

TL;DR

  • AMD announced Helios rack-scale solutions entering production in July 2026. Product availability and delivery dates still depend on the chosen OEM system.
  • The published architecture combines 72 MI455X GPUs, 18 EPYC “Venice” CPUs and Pensando networking in an Open Rack Wide arrangement.
  • Use the up-to-246 kW figure from the AMD/Schneider reference design to understand the planning scale. Obtain the selected OEM’s actual load schedule before sizing infrastructure.
  • Confirm loaded dimensions, mass, movement routes and maintenance space; a wider rack cannot be converted into a rack count by a simple width ratio.
  • Request liquid and residual-air heat loads separately, together with coolant, pressure, temperature and control requirements.
  • Keep compute-rack load, network/support IT and total facility input as separate quantities.
  • Our late-October commercial indications suggest a potentially lower acquisition price and shorter equipment lead time; comparison scope, software readiness and site readiness still determine the business case.
  • ModulEdge’s dedicated Helios facility design is now MDC3000: ten compute racks, 16 supporting IT racks, 2.75 MW target IT load and 3.2 MW total incoming power.

What Helios is, and what is available in 2026

AMD’s Helios product information describes a reference design for OEM and ODM implementation. It combines the MI455X GPU architecture, Venice processors and Pensando networking with centralized rack power and liquid-cooling interfaces. Open Rack Wide geometry is part of that design approach.

AMD’s 23 July 2026 announcement states that Helios rack-scale solutions are now in production and specifies 72 MI455X GPUs and 18 Venice CPUs. This is a more current status statement than the product-page FAQ’s earlier expectation of volume availability in the second half of 2026.

Production status does not settle which configuration you can purchase, its regional electrical arrangement or its committed delivery date. Obtain those details from the OEM quotation. Keep a versioned equipment schedule so that a later change in power shelves, network equipment or service requirements triggers a facility review.

For the broader process of translating a workload into infrastructure, see our GPU data center planning guide.

AMD Helios vs NVIDIA GB300 NVL72: what is the difference?

AMD Helios and NVIDIA GB300 NVL72 both integrate 72 GPUs at rack scale. They use different processors, GPU interconnects and software stacks. Matching the GPU count does not make their performance, installation requirements or ownership cost equivalent.

AMD Helios vs NVIDIA GB300 NVL72 — platform and buying considerations
AreaAMD HeliosNVIDIA GB300 NVL72
Compute72 Instinct MI455X GPUs with EPYC “Venice” host CPUs72 Blackwell Ultra GPUs with 36 Arm-based Grace host CPUs
GPU fabricUALink-based scale-up architecture; AMD describes UALink over Ethernet in its rack designNVLink connects the 72-GPU scale-up domain
Software routeROCm, supported frameworks and serving tools; assess HIP porting for custom CUDA codeCUDA and NVIDIA libraries; retain and validate the application’s NVIDIA software path
Rack and coolingOCP Open Rack Wide design with rack liquid-cooling interfacesLiquid-cooled rack-scale architecture with its own OEM installation requirements
Price and deliveryOur dated indications suggest a potential acquisition-price and lead-time advantage; obtain a matched offerCompare the actual GB300 NVL72 configuration, support scope and delivery milestone in the offer
ValidationModel fit, serving performance, migration effort, support and complete facility interfacesThe same workload, quality and latency targets, support scope and complete facility interfaces

The hardware distinctions above come from the AMD Helios platform description and NVIDIA GB300 NVL72 specifications. For software, CUDA is NVIDIA’s GPU programming platform; ROCm provides the AMD route. A shared framework name does not make the underlying libraries, custom kernels or operational procedures interchangeable.

Our view is that an established NVIDIA application with extensive CUDA-specific work may justify staying with NVIDIA even when an AMD equipment offer is lower. Helios deserves a workload trial when the supported AMD stack meets the application requirements and the resulting acquisition cost, availability or serving economics improves the project. The migration and validation effort belongs in that comparison.

A facility designed around one rack cannot be assumed suitable for the other. Obtain each OEM’s electrical, liquid and residual-air duties, structural loads, dimensions and maintenance clearances. The Helios reference-design power envelope discussed below is not a GB300 NVL72 rack rating, and neither platform’s peak compute specifications predict the accepted tokens your application will produce.

Why enterprises are considering AMD Helios

In our enterprise discussions, the initial hardware shortlist often starts with the platform a team already knows. NVIDIA is usually that familiar starting point. AMD becomes a serious option when the proposed budget or delivery date no longer fits the project. This is our experience of those conversations, rather than a claim about the whole market.

We have also received AMD inference enquiries for internal applications and services delivered to enterprise customers. Those requirements do not all call for Helios: a rack-scale system has to earn its place through workload demand, utilization and the operating plan. Interest in AMD chips should not be mistaken for a requirement to buy a complete Helios deployment.

Our view on Helios pricing and delivery times

Commercial indications discussed with us in late October 2026 put Helios-based acquisition pricing roughly 30–40% below the compared GB300 NVL72 configuration. We see that as a reason to investigate the alternative seriously. The configurations and supply scopes have not yet been reconciled into a like-for-like quotation, so the percentage is a budgeting indication, not a published price or a general discount.

The same discussions indicated roughly 2–3 months for Helios-based systems versus 8–10 months for GB300 NVL72. These are our dated commercial observations, not supplier delivery commitments. Before using them in a business case, obtain a current written offer and establish whether its date means shipment, arrival, installation or accepted production service.

Lower acquisition cost can leave more capital for the network, electrical infrastructure, cooling or operations. Earlier useful capacity can bring forward an internal deployment or customer onboarding. Neither advantage survives automatically: software migration can consume the price difference, and a rack delivered before the site has power does not bring the service online.

We also expect the higher-power MDC3000 infrastructure to cost more than MDC2000 infrastructure. A lower compute-equipment price therefore needs to be assessed against the complete facility and equipment package. We do not treat a hardware-price indication as a 30–40% reduction in total project capital expenditure.

Questions to put beside a Helios quotation
DecisionCompare on the same basisWhat can change the result
Acquisition costCompute, networking, storage, support, taxes and delivery scopeAn omitted service or different configuration can outweigh the headline difference
Time to useful computeEquipment date, software readiness, site power and acceptance milestoneEarlier shipment can still lead to later production service
Operating costUseful workload, utilization, energy, maintenance and software effortLower capex does not guarantee lower serving cost
InfrastructureComplete IT load, cooling plant, resilience and site worksDifferent facility boundaries make price-per-MW comparisons misleading

Enterprise AI and token factories need different business cases

An enterprise may justify infrastructure through internal productivity, service quality, data control or avoided external spending. An inference operator selling tokens has a revenue model: the useful output must cover the cost of supplying it. Both need adequate performance, but their reasons to own compute are different.

For an inference business, compare cost at the response time and quality customers will accept. A useful calculation is: cost per million accepted output tokens = total cost for the period ÷ (accepted output tokens in that period / 1,000,000). State whether total cost includes capital recovery, financing, power, facility operation, software engineering and support. Define accepted output consistently, including the quality and latency thresholds.

A lower price per GPU can improve this calculation, but utilization, memory fit and serving software can change its denominator. For an enterprise workload, also ask how often the system will be used and whether a smaller deployment or hosted capacity meets the need. Our on-premise AI inference guide examines that ownership decision separately.

Software readiness belongs in the Helios buying decision

The recurring concern in our enterprise conversations is whether the team can migrate, optimize and support the workload. A buyer may accept the hardware economics and still hesitate over the software work. Our view is that AMD is making the option easier to evaluate, but a credible proposal must show the buyer a supported software route and who will make it work.

Framework support, HIP and CUDA compatibility are different questions

ROCm is the AMD software platform. Supported versions of frameworks such as PyTorch and serving tools such as vLLM can provide an AMD execution path. Confirm the exact GPU, operating system, driver, framework, model and serving features; support for a framework name alone does not validate a complete application.

HIP and HIPIFY provide a route for porting CUDA source code. AMD explicitly describes manual coding and performance tuning as possible parts of that work. A framework-based application and a codebase with custom kernels, extensions or proprietary dependencies can therefore have very different migration effort.

Third-party compatibility projects need their own assessment. SCALE describes compilation of CUDA source for AMD hardware; its developer documentation is a statement of that toolkit’s approach, not evidence that an intended Helios workload is qualified. The ZLUDA FAQ, checked for this update, excludes server-class GPUs. It should not be used to justify Helios production readiness.

How to use the MI355X benchmark in a Helios evaluation

The SemiAnalysis InferenceX Kimi K3 comparison circulated in our late-October discussion is useful because it connects serving economics to software optimization and memory fit. The 27 October 2026 chart we reviewed compares MI355X with B200 for Kimi K3 2.8T, plotting total tokens per dollar of TCO against P90 interactivity. It is evidence about those systems and that workload; Helios uses MI455X.

The accompanying analysis attributes the reported advantage to software optimization and keeping the workload within one server because of memory capacity. The chart uses large-hyperscaler ownership assumptions of $1.50 per MI355X chip-hour and $1.73 per B200 chip-hour. Those are model inputs, not rental prices or quotations an enterprise buyer should expect to receive.

Our takeaway is to test the model, memory layout and serving stack together. We are not transferring the chart’s advantage to Helios or claiming a universal vendor performance ranking. Before quoting a multiplier, review the original run configuration, accuracy settings and cost model; a screenshot of one run cannot settle those questions for a different deployment.

Validate the workload before committing to the rack

Use the same model version, numerical precision and quality threshold on each candidate. Then record the conditions that make the result useful to your application:

  • Input and output lengths, context window, concurrency and expected traffic pattern.
  • Time to first token, inter-token latency and tail latency at the service level you intend to offer.
  • Sustained accepted throughput, memory use and the number of servers or racks required.
  • Energy for the measured workload, together with the facility-energy boundary used in the cost model.
  • Engineering effort, regression testing, observability, upgrade process and the team responsible for support.

Faster procurement and faster inference are separate benefits. The useful comparison is the date and cost at which a supported workload can enter service, with the capacity and response time the buyer needs.

How much power does a Helios rack need?

The AMD/Schneider Electric reference-design announcement describes support for racks up to 246 kW. It reports an ANSI-based design for the US market, with an IEC extension planned. That figure and jurisdiction belong to this reference design; neither is a universal specification for every OEM Helios deployment.

A facility engineer needs several quantities that a single headline kilowatt figure cannot supply:

  • Maximum rack input: the supplier’s specified electrical input for the selected equipment and operating limits.
  • Expected operating load: a workload-based estimate used for energy and staged-capacity planning.
  • Supply behavior: voltage, frequency, phases, power quality, connection arrangement and response to loss of a feed.
  • Dynamic behavior: permitted power steps, startup sequence and any controls that limit or coordinate demand.
  • Support load: networking, storage and other equipment outside the compute-rack schedule.

Ask the OEM to identify the measurement boundary and any included conversion losses. Size protective devices, conductors and supply equipment against the agreed design case and applicable electrical requirements. An expected average workload does not replace the equipment’s supported maximum input or its fault and maintenance cases.

Our data center power distribution guide follows the path from site connection to rack. A Helios project needs that path documented using the chosen rack’s actual interfaces.

A four-rack calculation establishes scale, not site capacity

Suppose an early study uses four racks at the reference-design envelope of 246 kW each:

Compute-rack input allowance = 4 × 246 kW = 984 kW.

This is an illustrative calculation, not a published ModulEdge configuration or a confirmed OEM load schedule. It excludes separate network and storage equipment, cooling auxiliaries, UPS losses and other facility loads. At six racks, the same assumed allowance becomes 1,476 kW. Changing the actual rack allowance changes the result proportionally.

Do not use 984 kW as the required utility capacity. Add the separately defined loads, model conversion and cooling losses at the site conditions, and check the agreed redundancy and maintenance cases. For phased deployment, distinguish equipment installed for the first phase from infrastructure reserved for a later phase.

Rack width changes layout and service access

Helios uses an Open Rack Wide approach. The purchasing package needs dimensional drawings for the actual assembled system, including its installed and transport states. Ask for connection locations, protrusions, doors, service zones, lifting provisions and loaded support reactions.

Width alone is an incomplete layout input. A double-width arrangement does not establish that one Helios rack can replace two standard positions in a previously drawn room. The maintenance route, liquid manifold, busbar access, cable bend space and adjacent equipment can determine the usable layout.

Check the full delivery route before fixing the building: road and unloading access, transport limits, module openings, floor transitions and the final rack movement. The rack’s operating mass and point loads also need a structural review. Reserve a practical route for replacing the largest serviceable assembly after the facility is occupied.

For a modular building, ask the infrastructure provider and OEM to review the same layout revision. Put dimensions, clearance requirements and equipment mass in the interface schedule. A visually plausible arrangement is insufficient if a rack cannot be installed or maintained through the proposed openings.

Liquid cooling leaves a separate air-side task

AMD’s reference architecture includes liquid-cooling manifolds and quick connections. The selected OEM must provide the thermal duties and operating limits for the complete rack. These include the heat transferred into liquid, the heat released into the room and the conditions under which those values apply.

Avoid assigning a generic percentage to Helios liquid heat capture. A facility design needs the actual thermal split for its equipment, including power and networking components. The room still needs a means of removing the residual air heat, and the site needs a path for rejecting the combined heat outdoors.

For the liquid interface, request the coolant specification, supply and return temperatures, required flow, pressure limits, pressure-drop curve, filtration and fluid-quality requirements. Identify who supplies the CDU, pumps, manifolds and control logic. Record whether limits apply at the facility connection, CDU or rack inlet; those are different measurement points.

The CDU sizing guide explains thermal and hydraulic selection. For Helios, feed it the OEM’s data instead of transferring a flow rate or temperature schedule from another GPU platform.

Outdoor cooling must be evaluated against the local design conditions and the required operation during equipment maintenance. A high allowable coolant temperature can create useful design options, but it does not by itself promise compressor-free operation, a fixed PUE or zero water consumption. The complete heat-rejection arrangement determines those outcomes. See our guides to liquid-cooling architecture and cooling in extreme heat.

Close the interfaces before issuing the facility specification

Use one interface schedule shared by the OEM, facility provider and site engineer. It should identify the responsible party, document revision and unresolved information for each connection.

InterfaceEvidence to obtainFacility decision it enables
Rack electrical inputLoad schedule, connection details and supply-loss behaviorDistribution, protection, UPS and power-path arrangement
Liquid connectionFluid, temperatures, flow, pressure limits and connector detailsCDU, pipework, pumping and heat-exchanger selection
Air heatResidual-air duty and required inlet conditionsRoom-air handling and cooling capacity
Structure and accessLoaded mass, support reactions, drawings and service envelopeFloor design, rack layout and movement route
Network and support ITEquipment schedule, power, cooling and cable requirementsSupport-space allowance and complete IT load
Controls and operationAlarms, power controls and agreed responses to faultsBMS/DCIM integration and operating procedures
AcceptanceSupported test conditions and supplier responsibilitiesFactory and site test plans with measurable acceptance criteria

Several items may remain provisional early in procurement. Mark them as such and identify which design decisions depend on them. For example, an unresolved rack connector can leave a pipework connection open without preventing a site survey. An unresolved maximum rack input can prevent final electrical sizing.

Commission the assembled system under the agreed operating cases

Acceptance should demonstrate the selected rack and infrastructure together. Record rack input, component temperatures, coolant conditions, residual-air conditions and useful workload during the agreed load test. A cooling-plant test without the relevant equipment behavior leaves a different question unanswered.

Agree how to test loss of a power feed, loss of a cooling component and planned maintenance. The procedure must be approved by the equipment suppliers; do not assume the rack will continue at full load or that every fault requires the same response. Record alarm destinations, control ownership and the conditions for restart.

Service access also deserves a witnessed check. Demonstrate a representative tray or component replacement using the planned lifting aids, disconnect procedure and work area. A commissioning record should show which operating cases were tested and which still rely on supplier documentation or a later site test.

Where ModulEdge fits a Helios deployment

Earlier ModulEdge guidance described Helios configurability under MDC2000. The dedicated Helios configuration is now designated MDC3000. The selected AMD/OEM rack needs its own facility design; configurability does not establish OEM certification or transfer GB300 rack counts, GPU counts or heat splits to Helios. Confirm the rack schedule, electrical and cooling interfaces, service space and acceptance criteria for that exact configuration.

MDC3000: a prefabricated facility for the Helios configuration

ModulEdge now identifies its dedicated Helios facility design as MDC3000. The current design figures separate compute racks, supporting IT and total incoming power:

MDC3000 current design figures — 1 November 2026
Design itemCurrent figure or directionBoundary
Helios compute racks8 wide-format racksExact OEM configuration and interfaces agreed by project
Supporting IT racks16 for networking, CPU and storagePart of the complete IT equipment schedule
Total IT load target2.75 MWOverall IT configuration; not a per-rack allowance
Total incoming power3.2 MW in the current designIncludes facility demand beyond IT; final connection study required
Cooling directionApproximately 85% liquid / 15% airActual thermal duties follow the selected OEM equipment and site design
External form and accessSame external dimensions and appearance as the existing modular platformIT-hall access openings are adapted for the wider Helios equipment

These are design figures, not measured operating results or an OEM certification. Do not multiply a generic Helios rack allowance by ten and treat the result as the MDC3000 load schedule. The 246 kW reference-design envelope discussed above belongs to its named reference design; the MDC3000 IT target includes its selected compute and supporting equipment. The 3.2 MW and 2.75 MW power figures do not establish annual PUE.

Prefabricated modular data centers let the facility team coordinate a repeatable power, cooling and service-space design with factory integration and testing. Site preparation can proceed alongside factory work once interfaces are agreed. The programme still has to include procurement, transport, connection and commissioning. Our modular and prefabricated procurement guide explains the scope distinctions to put in the contract.

Decide whether an eight-rack unit fits the workload

Some enterprises do not need an eight-compute-rack deployment. Substantial software migration, low utilization or an established operating environment can outweigh an acquisition-price advantage. Start from the useful capacity required rather than filling a module because rack space exists.

If a phased deployment is proposed, agree how partial population affects power, cooling, controls, acceptance and operating cost. Phased population of MDC3000 is a project-design question, not an automatic capability established by the full-load target. For a colocation project, align the facility with the prospective tenant’s hardware and operating requirements.

Before moving from an indicative budget to procurement

  • Obtain a dated equipment offer with its bill of materials, scope exclusions and delivery milestone.
  • Agree the workload benchmark, quality and latency thresholds, migration effort and software support owner.
  • Reconcile the complete IT-load and thermal schedules with the site connection, outdoor plant and availability requirements.
  • Confirm installation and maintenance access for the selected rack, then align equipment arrival with site readiness and acceptance.
  • Compare the resulting total cost and useful capacity against the enterprise objective or inference-service revenue case.

Frequently asked questions

Is Helios a complete AMD product that I can buy directly?

AMD describes Helios as a reference design for OEM and ODM implementations. Purchase and support terms follow the system offered by the selected supplier.

Is Helios still only a future roadmap item?

AMD’s July 2026 announcement states that Helios rack-scale solutions are in production. Confirm availability and delivery for the exact OEM configuration and market you intend to buy in.

Does every Helios rack draw 246 kW?

No universal rating follows from that figure. The AMD/Schneider reference design supports racks up to 246 kW; obtain the selected OEM’s input schedule for your facility design.

Can I use a GB300 rack layout for Helios?

Only after reviewing the actual dimensions, service clearances and interfaces. Do not transfer rack counts, support allowances or electrical and thermal totals between platforms.

Does liquid cooling remove the need for room cooling?

The facility still needs to handle the selected equipment’s residual-air heat. Request separate liquid and air duties and check their operating conditions.

Can MDC2000 accommodate Helios-class infrastructure?

Earlier guidance described MDC2000 configurability. The dedicated AMD Helios configuration is now named MDC3000. Rack quantity, internal layout, resulting IT capacity and facility interfaces depend on the selected configuration and engineering review.

AMD Helios vs NVIDIA: which is better for enterprise AI?

Compare Helios with a named NVIDIA system such as GB300 NVL72 on the actual workload. Helios uses AMD Instinct GPUs and the ROCm software path; GB300 NVL72 uses Blackwell Ultra GPUs and CUDA. The useful choice depends on accepted performance, software migration and support, matched equipment offers, and facility readiness. GPU count or one benchmark does not establish a universal winner.

What does an AMD Helios system cost?

There is no universal price for the complete purchased configuration. Our late-October 2026 discussions indicated acquisition pricing around 30–40% below the compared GB300 NVL72 configuration, with scope still to be reconciled. Use it as our indicative commercial view; obtain a current, matched written quotation for a purchase decision.

Can existing CUDA applications run on a Helios deployment?

Some applications have supported framework and serving routes on ROCm. Custom CUDA code can require porting through HIP and HIPIFY, manual changes and performance tuning. Verify the application, dependencies and support arrangements on the selected hardware; generic compatibility claims do not establish production readiness.

Is MDC3000 rated at 3.2 MW of IT load?

The current MDC3000 design targets 2.75 MW overall IT load, with 3.2 MW total incoming power. Its layout has ten Helios compute racks and 16 network, CPU and storage racks. The final load schedule, cooling configuration and site design remain project-specific.

Bring the rack list. Or the site plan.

You do not need a finished specification. Send what is known, and we will identify the closest modular data center product and the decisions still standing between it and the site.